Interface were responsible for designing , procurement of and full supervision and installation of cabling systems and building services associated with the major upgrade to the waste water plant at Davyhulme – Manchester.

The upgrade consists of the decommissioning of parts of the existing plant and building new ASP lanes and a new Inlet works. Interface carried out the phase 1 of the upgrade works for Black and Veatch ( SBAP ). This current phase 2 of works is being undertaken by Laing O’Rourke.

Project Details

DATE

February 21st, 2016

CLIENT

Davyhulme Wastewater Plant

PROJECT TYPE

Wastewater Treatment

CONTRACTOR

Laing O’Rourke