Glasgow Waste Recycling Facility – Viridor

This project with a sub contract value in excess of £10M is our largest project to date. Sub contracted to Interserve Construction whom we worked very closely with to develop the coordinated 3D model. Our scope of work after we had designed the project in 3D involved 11000volt cabling, power , control and instrument cabling throughout the plant.The project covered a wide range of working conditions ranging from confined spaces, working at height, Compex installations and profibus commissioning.

We also supplied and installed a complete trace heating system to all exposed process piework.